How to estimate task durations accurately for time blocking, with room to spare

Estimate each task from how long similar tasks really took you, split anything bigger than one block into parts, and write the estimate down so you can compare it with the actual time. Then plan less than the week holds, with buffer between blocks and some hours left open.

Feature guideUpdated 14 min read

To estimate task durations accurately for time blocking, base each estimate on how long similar tasks really took you, and treat the plan in your head as the hopeful case. Split anything longer than one block into parts you can picture, write an estimate in minutes before you start, and note the actual time when the block ends. After a few weeks, that log shows how far your guesses usually run over, and you plan the week with that margin built in: buffer between blocks and part of every day left open.

This guide covers what the original research on the planning fallacy found, six steps for better estimates, how to keep a week from filling past what it can hold, and what planner apps say about their estimate features. The second half shows how to keep an estimate and actual log in Barside, a free desktop app for Windows, Linux and Mac. Barside has no timer, so every actual time in that log is one you type yourself.

Why time estimates run short: the planning fallacy

The 1994 paper below credits Daniel Kahneman and Amos Tversky with naming the planning fallacy in 1979, in "Intuitive prediction: Biases and corrective procedures", published in TIMS Studies in Management Science. A chapter with the same title appears as chapter 30 of the 1982 book Judgment under Uncertainty, from Cambridge University Press. It separates two kinds of evidence a forecaster can use: singular information about the case in front of you, and distributional information about how similar cases turned out. The 1994 paper calls the 1979 work a theoretical analysis of the planning fallacy.

Roger Buehler, Dale Griffin and Michael Ross tested the idea in Exploring the "Planning Fallacy": Why People Underestimate Their Task Completion Times, published in the Journal of Personality and Social Psychology in 1994 (volume 67, pages 366-381). The paper reports five studies with psychology students. In their words, "Distributional information concerns how long it took to complete other, similar tasks." Their Study 1 is the clearest case: 37 psychology students in the final semester of the Honors Thesis course at the University of Waterloo, in Ontario, Canada, predicted when they would hand in their thesis, and the course coordinator recorded the real dates. The averages below cover the 33 students in the analysis.

What the students were asked forPredicted, on averageTook, on averageFinished by that date
Their best estimate33.9 days55.5 days29.7%
The date "if everything went as well as it possibly could"27.4 days55.5 days10.8%
The date "if everything went as poorly as it possibly could"48.6 days55.5 days48.7%

Two details in that study matter for anyone who time blocks. Fewer than half of the students finished by their worst-case date, and their worst-case dates still came before the real ones on average, though the paper notes that this last gap was not statistically significant. The paper also reports that worst-case estimates were no more accurate than best estimates: the average gap between predicted and real dates was 23.2 days for the worst case and 22.6 days for the best estimate. Padding a guess is a different fix from checking it against your past. In Study 3, 78 undergraduate psychology students thought aloud as they predicted, and in the 67 recordings the researchers could hear, on average 74% of what people said was about future scenarios and 7% about relevant past experiences, which is the plan in your head at work.

The paper also tested other people as forecasters. In Study 5, 123 undergraduate psychology students predicted when someone else would finish an assignment. Their predictions were longer than the ones the original students had made for themselves, 8.5 days against 5.5 days on average, but no more accurate, because they erred in the other direction. Asking a colleague gives you a second view, and a log of your own similar tasks gives you a record to check both views against.

How to estimate task durations accurately for time blocking

To estimate task durations accurately for time blocking, start from your record of similar work and then adjust for what is different this time. The six steps below get quicker once your log holds a few weeks of rows.

  1. Split the task into parts you can picture. "Write the report" hides the outline, the data pull, the draft and the edit. Give each part its own estimate, and plan any part longer than one block as two blocks.
  2. Find two or three similar tasks you finished. Look for the same kind of work at a similar size, such as last month's report or the last client proposal. This is the distributional information Kahneman and Tversky describe.
  3. Link that past to this task in one sentence. Write something like "The last two reports took four hours each because the data came late, and this time the data is ready." This is close to what Buehler, Griffin and Ross asked people to do in their Study 4.
  4. Write the estimate in minutes before you start. A written number is one you can check later, and minutes are easier to compare than "a morning".
  5. Note the actual time when the block ends. Add a word on why it ran long, if it did: interruptions, scope, waiting on someone.
  6. Adjust new estimates by your own ratio. Divide your total actual minutes by your total estimated minutes for one kind of work, and multiply new estimates of that kind by the result.

Step 3 is close to what the 1994 paper tested. In Study 4, 123 undergraduate psychology students predicted when they would finish a computer assignment that took about an hour. Some first recalled similar past assignments, then worked out when they would finish if they finished as far ahead of the deadline as they usually did, and wrote a likely scenario based on that past. Of those students, 60.0% finished by their predicted time, against 38.1% of students who only recalled their past and 29.3% in the control group, and the paper found no significant difference between those last two groups. The paper adds that their predictions were no more accurate in absolute terms and that the step did not change when people finished, so it removed the hopeful lean without making the estimates exact. The authors also say they cannot rule out that writing the scenario, more than recalling the past, made the difference.

An example estimate

Example (made up): Dana, a freelance copywriter, has to write five onboarding emails for a client. Her gut says three hours. Split into parts, it reads: outline 30 minutes, drafts 120 minutes, edit 45 minutes and the client's notes 30 minutes, for 225 minutes. Her log shows that her last eight drafting tasks were estimated at 600 minutes in total and took 780, a ratio of 1.3. She plans 225 minutes times 1.3, about 290 minutes, as two morning blocks with a gap after each one.

How to avoid overbooking your week with time blocking

To avoid overbooking your week with the time blocking technique, plan fewer hours of estimated work than the week has free, and decide in advance where the overflow goes. Better estimates help, but the 1994 results suggest that some tasks will still run long, so the plan needs room for them.

These weekly schedule tips for time blocking keep a plan that bends when a day changes:

  • Put fixed meetings in first. Then place your hardest work in the open stretches around them, with the biggest task of the day in your best hours.
  • Leave buffer between blocks. Back-to-back blocks pass every overrun on to the next one, and a gap after each long block takes the overflow.
  • Keep part of every day unplanned. One open hour in the afternoon, as the daily planner template suggests, absorbs a call that runs late.
  • Give reactive work its own blocks. Email and chat spill into every block when they have none of their own.
  • Give each day one main task. Keep the other tasks small enough to move.
  • Total the week before it starts. Add up your estimates, multiply by your ratio, and compare the result with the hours you have free.
  • Decide what moves first. Mark one or two tasks a day that can slide to tomorrow when a block breaks.

We found no study that sets one right amount of buffer for everyone, so let your own log set it. If your actual times run 1.3 times your estimates, plan estimated work for no more than about three quarters of your free hours.

A weekly capacity check

Example (made up): a 40-hour week with 9 hours of meetings and 6 hours of email and chat blocks leaves 25 free hours. With a ratio of 1.3, about 19 hours of estimated work fills those 25 hours, since 19 times 1.3 is 24.7. So Lee, a product manager, plans about 19 hours of estimated tasks and leaves the rest open. Use your own hours and your own ratio in place of these.

Templates, and notes that write themselves on a schedule · Open the video

What planner apps say about estimates and actual time

Some planner apps build estimates into each task. Two describe how on their own help pages, as of November 2026:

  • Sunsama. Its user manual page on planned and actual times says "Planned time is used to set time estimates on your individual tasks." It adds that "The cumulative total of the planned times for your tasks make up your workload total for the day." You log actual time with the clock icon on a task, the E shortcut or the Task Timer (Spacebar), and a setting in your account settings can count planned time as actual time. The page also says "The workload counter will show red if your planned times exceed your workload threshold."
  • Motion. Its help article on how auto-scheduling works says "A duration must be provided before Motion can place the task." It splits long tasks into smaller blocks that respect a minimum block size, and it flags a task it can't place with the state "Could not fit".

Both do things Barside does not. Sunsama's Task Timer logs actual time as you work and its workload counter shows red when your planned times pass your workload threshold, and Motion places tasks in your schedule for you. Barside leaves the placing and the timing to you, and keeps your estimates in a note you can sort, filter and total. To compare planners that schedule for you, read AI planner apps that auto schedule tasks and whether Motion is worth it for freelancers.

Keep an estimate and actual log in Barside

Barside puts database tables in your notes: each column has a type, and you can sort, filter and total the rows. One table can hold every estimate beside its actual time.

  1. Make a note called Estimates log. Type / and choose Database table, or press Insert a database table under More formatting in the note toolbar. Give the table a title in Untitled table, such as Estimates.
  2. The table starts with Name, Status and Date columns. Click Name and rename it Task. Click Status, rename it Kind, and under Options rename its choices to kinds of work, such as Writing, Admin and Calls.
  3. Press the + after the last column to add Estimate, Actual and Ran over. In each column's menu, set Type to Number for the first two and Checkbox for the third.
  4. Under Estimate and Actual, choose Calculate, then Sum. Under Ran over, choose Percent checked.
  5. Add a row for each block: the task, its kind, the date, your estimate in minutes before you start, and the actual minutes when you stop. Tick Ran over when the actual passed the estimate.

Example (made up) of a few rows:

TaskKindDateEstimateActualRan over
Onboarding email draftsWritingNov 2120165Ticked
Send invoicesAdminNov 23025Not ticked
Prepare client callCallsNov 33045Ticked

Then read the table like this:

  • Your ratio. Divide the Sum under Actual by the Sum under Estimate. A database table has no formulas, so this one division is yours to do.
  • Your similar tasks. Press Filter, then Add a filter, and pick Kind is Writing. The totals count only the rows that show, so switch the total under Actual to Average to see how long a writing block takes you.
  • How often you run over. Percent checked under Ran over gives the share of blocks that broke their estimate.
  • Latest first. Choose Sort descending in the Date column's menu.

To see it as bars, type / under the table and choose Chart. The chart groups the rows by the first Choice column, Kind, and in Chart settings you can set Value to the Average of Actual, so each kind of work gets its own bar. See charts in notes.

Plan the week and mark the blocks that broke

Plan the week in its own note. The weekly planner template gives you three goals and a board with a column for each day. For hour-by-hour blocks, use a Time blocks note with a plain table: choose Insert table under More formatting, with columns such as Time, Block and Estimate, and give the buffer an empty row of its own.

When a block breaks, select it, choose Strikethrough under More formatting in the note toolbar, and write the new time in the row below. The crossed-out line keeps a record of how the day went. Add each broken block to your log as a row with its real time. The time blocking guide covers the rest of the daily routine.

For a nudge at the start of each block, write the block as a checklist item, like 10:30 Client call, press the bell at its end and pick the time. Barside's Calendar view shows today and the next 7 days from Google Calendar or Outlook, through each calendar's private iCal address, so your meetings sit beside the plan. It only reads calendars and never adds, moves or deletes events, so blocks you want on your calendar go into Google Calendar or Outlook. See the calendar next to your notes.

Review your estimates every week

The weekly review is where the log pays off. Start a note from Barside's built-in Weekly review template, which has Wins, What did not go well, Next week's priorities and Notes, and add the four questions below. Open Note options and choose Save as template. Then, in Settings, find Templates & repeating notes, click Templates, then New repeating note. Pick your template and a workspace, choose Weekly under Repeats, tick Friday, set the Time and click Save. Barside then makes a fresh review note each week and shows a quiet New note ready notification.

  1. What was this week's ratio of actual to estimated minutes, and which kind of work had the highest?
  2. What does Percent checked under Ran over say, compared with last week?
  3. How many blocks did you strike through, and what broke most of them?
  4. How many hours of estimated work fit next week, once you divide your free hours by your ratio?

For a fuller checklist around the same habit, see the GTD weekly review.

Limits and privacy

  • No timer. Barside has no timer or countdown, so it doesn't record how long a block took. You type each actual time yourself. If you want a countdown inside a block, use a separate timer, as the Pomodoro Technique guide suggests.
  • No formulas. A table totals columns with Sum, Average, Min and Max, and it can't compute a difference or a ratio for each row.
  • A read-only calendar. Barside reads Google Calendar and Outlook and doesn't create events or place tasks for you.
  • Size. A table holds up to 50 columns and 2,000 rows, and long tables show 100 rows at a time.
  • Systems. Tables work the same on Windows 10 and 11, on Linux and on Mac.
  • Where it lives. A table is saved inside its note, in your library on your computer. Its contents are not uploaded unless you turn on cloud sync or cloud backup with Barside Plus, or share the note to a Space. Read the privacy guide.
  • Cost. Barside is free. Barside Plus is optional at US$20 a month or US$200 a year and adds cloud backup and sync between computers, and the log above doesn't need it.

Works well with

FAQ

Questions and answers

How do you estimate how long a task will take?

Start from how long two or three similar tasks really took you, then adjust for what is different this time. Split the task into parts you can picture, write the estimate in minutes before you start, and note the actual time when you stop. After a few weeks, divide your total actual minutes by your total estimates and multiply new estimates by that ratio.

Why do my time estimates always run short?

Researchers call it the planning fallacy. In Buehler, Griffin and Ross (1994), psychology honors students at the University of Waterloo predicted they would hand in their thesis in 33.9 days on average and took 55.5 days. In another of their studies, people thinking aloud focused mostly on future scenarios while they predicted, and less on how similar tasks had gone before.

How much buffer should I leave between time blocks?

We found no study that sets one amount for everyone, so let your own record decide. Keep a log of estimates and actual times, and if your actual times run 1.3 times your estimates, plan estimated work for no more than about three quarters of your free hours. Leave a gap after each long block and one open hour in the afternoon.

How do I avoid overbooking my week with time blocking?

Put fixed meetings in first, give reactive work like email its own blocks, and give each day one main task. Before the week starts, add up your estimates, multiply by your ratio of actual to estimated time, and compare the result with your free hours. Mark one or two tasks a day that can move to tomorrow when a block breaks.

Does Barside track my time automatically?

No. Barside has no timer or countdown, so you type each actual time yourself, for example in a Number column of a database table. If you want a timer that logs actual time as you work, Sunsama's user manual describes a Task Timer for that.

Can a Barside table work out the difference between my estimate and the actual time?

Not row by row. A database table has no formulas. It can total a Number column with Sum, Average, Min or Max for the rows that show, so you divide the Sum under Actual by the Sum under Estimate yourself to get your ratio. A Percent checked total under a checkbox column shows how often blocks ran over.

Is Barside free?

Yes. Barside is free on Windows, Linux and Mac, and its notes, database tables, templates and calendar view need no account and no AI. Barside Plus is optional at US$20 a month or US$200 a year and adds cloud backup and sync between computers. An estimate log doesn't need it.

Sources

Where the facts come from

Checked on November 17, 2026. Products change: if something here is out of date, tell us at support@barside.space.

  1. Buehler, Griffin and Ross (1994): Exploring the "Planning Fallacy": Why People Underestimate Their Task Completion Times (University of Florida copy)
  2. Cambridge University Press: Kahneman and Tversky, Intuitive prediction: Biases and corrective procedures (Judgment under Uncertainty, chapter 30)
  3. Sunsama User Manual: Planned and Actual Times
  4. Motion Help: How Auto-Scheduling Works: Behind the Scenes